Project Background
After an earlier AGV material-handling project, the manufacturer required a warehouse modernization to improve storage density, inventory control, and handling efficiency for semi-finished materials.
Project Objectives
- Automate semi-finished material storage and warehouse logistics.
- Support end-of-line automatic putaway and pull-based inbound supply for downstream processes.
- Replace repeatable manual warehouse transport with driverless material handling.
On Site Assessment and Data Analysis
The warehouse analysis covered SMT and insertion buffer inventory, storage categories, and inbound/outbound flow. The calculated design considered 120 SMT carts per day and 105 insertion carts per day, together with the required storage and transfer capacity.
Facility Layout

Solution Approach
The upgrade combined stacker storage and retrieval, central control, wireless communication, capacity and workflow planning, floor and fire-preparation review, docking preparation, and AGV machine-side transfer. WMS and WCS were included for warehouse execution and control.
Warehouse Workflow and Control Logic
Semi-finished materials move from production to ASRS storage through automated putaway. WMS and WCS coordinate storage locations, stacker-crane tasks, conveyor interfaces, and pull-based release to downstream operations.

Equipment Overview
| Artículo | Especificación |
|---|---|
| Stacker crane payload | Up to 25 kg |
| Travel speed | 1 m/s |
| Lift speed | 0.5 m/s |
| Travel accuracy | ±5 mm |
| Lift accuracy | ±3 mm |
| Control | PLC with industrial wireless communication |

Project Scope and ROI Analysis
| Alcance | Quantity / detail |
|---|---|
| Stacker cranes | 5 units |
| Tray storage locations | 2,776 |
| Conveyor sets | 10 units |
| WMS / WCS | Warehouse management and control |
| Labor reduction | 3 warehouse operators |
Project Results
The project defined a connected ASRS upgrade for automated storage, retrieval, and production interface handling. The legacy assessment estimated a reduction of three warehouse operators and a three-year payback period.